Portfolio filters
Showing 71 of 71 villas. Filters update portfolio summaries and highlight matching map units.
Villas in view
71
71 villas in workbook
Average progress
17%
Weighted unit progress
Completed activities
314
2,840 tracked work items
Reporting blocks
4
Blocks 38, 39, 40 and 41
Click a numbered villa to open its construction record.

Block 38 · VILLA · C10
Weighted progress
56%
Forecast completion
24 Oct 2026
5
Complete
27
In progress
8
Not started
Villa information
- Contractor
- SALD
- Package
- Package - 7
- Cluster code
- C10
- Orientation
- STANDARD
- Design style
- MODERN
- Color shade
- C
- Model
- C10
- Neighborhood
- SE3
Live site records linked to this villa. Open any photo to view its original quality.
Average weighted progress and villa count across the filtered population.
Average completion across the filtered villa population.
Progress and target/final-point dates from the workbook.
MCC — AL AROUS · Zone A, NBH SE3
Summary time schedule
Target finish dates by activity group and block — Blocks 38–41
23 Aug 26
Activity groups
14
Blocks tracked
4
Programme start
31 Aug 26
Programme finish
13 Nov 26
Total span
74 days
Each finish date is the latest target finish date among the underlying activities in that group for all units in the block. Click a block chip to isolate it · hover a bar for dates and duration · dashed amber line = data date.