MCC · AL AROUS · Zone A

Construction tracking dashboard

Interactive progress reporting for Blocks 38–41. Select a villa from the map or use the filters to review its construction activities and forecast dates.

ROSHN Alarous logoAJI logoFinal Point Contracting Company logo

Workbook data date

23 Aug 2026

Baseline workbook · Live photos

Portfolio filters

Showing 71 of 71 villas. Filters update portfolio summaries and highlight matching map units.

Villas in view

71

71 villas in workbook

Average progress

17%

Weighted unit progress

Completed activities

314

2,840 tracked work items

Reporting blocks

4

Blocks 38, 39, 40 and 41

Interactive villa map

Click a numbered villa to open its construction record.

Selected villaFilter match
Aerial ALAROUS construction plan showing selectable villas 414 through 484
Villa 414
In progress

Block 38 · VILLA · C10

Weighted progress

56%

Forecast completion
24 Oct 2026

5

Complete

27

In progress

8

Not started

Villa information

Contractor
SALD
Package
Package - 7
Cluster code
C10
Orientation
STANDARD
Design style
MODERN
Color shade
C
Model
C10
Neighborhood
SE3
Villa 414 progress photos

Live site records linked to this villa. Open any photo to view its original quality.

0 photos
Loading progress photos
Progress by block

Average weighted progress and villa count across the filtered population.

Block 389 villas
52%
Block 3922 villas
17%
Block 4022 villas
8%
Block 4118 villas
8%
Portfolio activity summary

Average completion across the filtered villa population.

1

Earth work

100%
2

Under Ground Utilities

100%
3

Villa Foundation

100%
4

Waterproofing for Foundation and Backfilling

100%
5

Plumbing works 2nd Fix

26%
6

LC Wiring

25%
7

UG Water Tank

25%
8

External Works(Interlock, Earth Pit/Elect & Telecom, Signage,External Lighting, etc)

22%
9

LV Cabling and wiring

20%
10

LC Wiring Devices

17%
11

Internal Lighting & Devices

17%
12

LV Works (Fittings, Main DB & Submain DB's)

17%
13

Electrical Meter

17%
14

Water Meter

14%
15

HVAC External units

12%
16

Water Heater

11%
17

External Painting (Primary & Final Finish )

11%
18

HVAC Internal units

10%
19

Ground Floor- Screed & Toping

10%
20

HVAC Works (Piping, duct, volume damper and etc)

10%
21

Solar System (Water Heater incl. Panel & Storage tank)

10%
22

First Floor- Screed & Toping a

9%
23

Roof Floor- Screed & Toping a

9%
24

Stairs Finishes

7%
25

Internal Painting (Primary & Final Finish )

7%
26

Wet Area Sanitary Fixtures and Accessories

7%
27

Internal Flooring and Skirting

7%
28

Concrete Floor Finish

7%
29

Installation of Windows

7%
30

Boundary wall

6%
31

Car Shade

5%
32

Roofing system

5%
33

Internal gypsum partition Wall (Closing of Openings)

5%
34

Wet area false ceiling

4%
35

Wet area waterproofing

3%
36

Wet Area Tiling

2%
37

Handrails

2%
38

Installation of Doors incl. Hardwares

1%
39

Install Kitchen Cabinets, Countertop and accessories

0%
40

Testing & Pre-Commissioning

0%
Villa 414 activity details

Progress and target/final-point dates from the workbook.

Earth work

100%
Target / final point: Recorded complete

Under Ground Utilities

100%
Target / final point: Recorded complete

Villa Foundation

100%
Target / final point: Recorded complete

Waterproofing for Foundation and Backfilling

100%
Target / final point: Recorded complete

Plumbing works 2nd Fix

95%
Target / final point: 10 Sept 2026

HVAC Works (Piping, duct, volume damper and etc)

30%
Target / final point: 10 Sept 2026

LV Cabling and wiring

80%
Target / final point: 10 Sept 2026

LC Wiring

100%
Target / final point: 10 Sept 2026

Wet area waterproofing

0%
Target / final point: 12 Sept 2026

Ground Floor- Screed & Toping

90%
Target / final point: 17 Sept 2026

First Floor- Screed & Toping a

80%
Target / final point: 17 Sept 2026

Roof Floor- Screed & Toping a

80%
Target / final point: 17 Sept 2026

Installation of Doors incl. Hardwares

0%
Target / final point: 20 Sept 2026

Installation of Windows

50%
Target / final point: 20 Sept 2026

Internal gypsum partition Wall (Closing of Openings)

80%
Target / final point: 21 Sept 2026

Wet area false ceiling

0%
Target / final point: 21 Sept 2026

Internal Painting (Primary & Final Finish )

50%
Target / final point: 26 Sept 2026

Internal Flooring and Skirting

30%
Target / final point: 01 Oct 2026

Wet Area Tiling

0%
Target / final point: 01 Oct 2026

Stairs Finishes

0%
Target / final point: 01 Oct 2026

Roofing system

10%
Target / final point: 21 Sept 2026

Concrete Floor Finish

20%
Target / final point: 24 Sept 2026

UG Water Tank

90%
Target / final point: 20 Sept 2026

External Painting (Primary & Final Finish )

80%
Target / final point: 01 Oct 2026

Boundary wall

50%
Target / final point: 02 Oct 2026

External Works(Interlock, Earth Pit/Elect & Telecom, Signage,External Lighting, etc)

80%
Target / final point: 11 Oct 2026

Handrails

0%
Target / final point: 05 Oct 2026

Water Heater

40%
Target / final point: 06 Oct 2026

Wet Area Sanitary Fixtures and Accessories

15%
Target / final point: 06 Oct 2026

Solar System (Water Heater incl. Panel & Storage tank)

25%
Target / final point: 06 Oct 2026

HVAC External units

15%
Target / final point: 06 Oct 2026

HVAC Internal units

15%
Target / final point: 06 Oct 2026

Internal Lighting & Devices

60%
Target / final point: 06 Oct 2026

LV Works (Fittings, Main DB & Submain DB's)

60%
Target / final point: 06 Oct 2026

LC Wiring Devices

60%
Target / final point: 06 Oct 2026

Install Kitchen Cabinets, Countertop and accessories

0%
Target / final point: 11 Oct 2026

Electrical Meter

60%
Target / final point: 08 Oct 2026

Water Meter

50%
Target / final point: 08 Oct 2026

Car Shade

10%
Target / final point: 14 Oct 2026

Testing & Pre-Commissioning

0%
Target / final point: 24 Oct 2026

MCC — AL AROUS · Zone A, NBH SE3

Summary time schedule

Target finish dates by activity group and block — Blocks 38–41

Data date

23 Aug 26

Activity groups

14

Blocks tracked

4

Programme start

31 Aug 26

Programme finish

13 Nov 26

Total span

74 days

Activity group
27 Aug
03 Sept
10 Sept
17 Sept
24 Sept
01 Oct
08 Oct
15 Oct
22 Oct
29 Oct
05 Nov
12 Nov
1. MEP Releasing Works
2. Wet Area Waterproofing
3. Screed Works
4. Installation of Doors & Windows
5. Internal Gypsum Partition Wall
6. Wet Area False Ceiling
7. Internal Painting (Primary & Final Finish)
8. Internal Flooring and Skirting
9. Wet Area Tiling & Stairs Finishes
10. Roofing System
11. External Painting (Primary & Final Finish)
12. External Works (Interlock, Elect/Telecom, Signage, Lighting)
13. MEP Final Fix Works
14. Testing & Pre-Commissioning

Each finish date is the latest target finish date among the underlying activities in that group for all units in the block. Click a block chip to isolate it · hover a bar for dates and duration · dashed amber line = data date.